Project Owner

City of Dodge City - Ray Slattery

Project Delivery Method

Design-Build

Project Duration

16 Months

Project Value

$16,385,000

Project Overview

Water Reclamation Facility and Beneficial Reuse Improvements

This design-build project was a new wastewater treatment facility built to keep up with future growth of Dodge City, including a casino, event center and hotel. The plant includes preliminary and advance secondary treatment with disinfection. The plant was designed to accommodate flows through the year 2030 with an average daily flow of 1.3MGD and future expansion to 2.5 MGD and Peak flow of 7.5 MGD. Elements of the project included:

• Influent pump station
• Fine Screening
• Advanced activated sludge treatment basin
• Membranes to clarify and filter stream
• Ultra-violet disinfection units for disinfection
• Sludge handling including centrifuge, conveyor and storage
• A beneficial reuse system including holding pond and pumping system

Infrastructure of this type is a critical element of continued economic development. Dodge City and its residents will benefit for many years with the construction of this WWTP and associated conveyance systems, providing capacity for increased residential, commercial and industrial growth.