Project Owner

Tenawa Haven Processing, LLC - Greg Ameringer

Project Delivery Method

Time and Materials

Project Duration

2 Months

Project Value

$1.05 Mil

Project Overview

Helium Plant Expansion Construction

Auger Cast Piles Drilled:                        106 EA
Concrete Poured:                                    973 CY
Anchor Bolts Set:                                   398 EA
Rebar Installed:                                        90 TN
Man Hours Worked:                                  6,612
Daily Safety Huddles Held:                           49
Hazards Recognized and Mitigated:            78
Average Weekly Walk Score:                    92%
Weekly Safety Briefings Held:                      10
Recordable Incidents:                                       0
Original Budget:                                     $1.4 mil
Billings:                                                  $1.05 mil